Re: Releasing Process Chains after a Refresh

DB49, Believe me, I tell them every year. Since these are scheduled via RSPC rather than SM37, BTCTRNS1&2 don't seem to have an effect.  After the client copy, the jobs for every master chain are...

View Article


How to get time series data

Hello All, I've been searching all over the forum, but I haven't got an answer. In transaction /SAPAPO/msdp_admin, you right-click a planning area and you can check "Created time series objects". There...

View Article


Re: Releasing Process Chains after a Refresh

Jeff,I don't know the exact method used by Basis in your company to conduct a 'refresh'.  However, I have never seen a refresh done whereby the refresh process MUST set the jobs to 'scheduled' status....

View Article

Re: How to get time series data

resolved FM is  /SAPAPO/TS_PAREA_VERSIO_GET

View Article

Planned Order End date is different in ECC and APO.

Hi All, Planned order created by SNP run (CTM) always has start and end date same in ECC. The same planned order when we check in ECC its different but same in ECC. There is one month of difference in...

View Article


Planned order avail/require date is same but having start date different in...

Hi All, Planned order created by SNP run (CTM) always has different start date  and end date same in APO. The same planned order when we check in ECC its different but same in ECC.   Example: Planned...

View Article

Re: Planned order avail/require date is same but having start date different...

Hi Deepika, The duration of the planned order is decided by the activity times from the PDS or PPM. Which is the same durations, you maintain in ECC routing.Since the system uses the backward...

View Article

Running Optimization with considering Shelf Life

In case of considering the shelf-life, how can I ran the optimizer with calculating Penalty costs for Continuing/Disposing Expired Products, I need a help of finding these details from the optimizer...

View Article


Re: Limit APO Capacity Consumption per bucket - SNP optimizer

Hi Ryan, Have you tried with defining the overload % as 85%, so that system will always try not to plan anything more than 85% on a bucket? Regards,Manimaran M.

View Article


Re: Planned order avail/require date is same but having start date different...

Real Eg is having below mentioned date issue.  In APOGRPT includes 2 daysPDT incluudes 0 daysPDS activities 13 days PDS in APO having below activities. Setup    5 dayssetup    1 daysproduce  1 daysetup...

View Article

Re: Planned order avail/require date is same but having start date different...

Hi mani, Thanks for your reply.Please find the below details.Real Eg is having below mentioned date issue.  In APOGRPT includes 2 daysPDT incluudes 0 daysPDS activities 13 days PDS in APO having below...

View Article

Re: Planned order avail/require date is same but having start date different...

Hi Deepika, Could you please post the screenshots of the APO planned order with date details and the ECC planned/production order?If possible, please post the routing screen as well. Regards,Manimaran M.

View Article

Image may be NSFW.
Clik here to view.

Re: Planned order avail/require date is same but having start date different...

Hi Manimaran, Please Find the attached images for RRP3/Routing/PDS/MD04Kindly let me know if you need more details.  RegardsDeepika

View Article


Image may be NSFW.
Clik here to view.

Re: Planned order avail/require date is same but having start date different...

View Article

Re: Planned order avail/require date is same but having start date different...

Hi Deepika, Since you are using SNP PDS, the time in the PDS would be rounded to the minimum of one day.So, in SNP, it would calculate the start and end date using this rough cut PDS.However, it seems...

View Article


Re: Assignment error: Overwriting of a protected field.

Issue Resolved, followed another approach. Thanks.

View Article

Re: APO DP - Manage forecast for multiple items sharing same total forecast

Hi Peter, thank you for the reply.I've another more challenging question where I hope you can help as well. In this case I've 2 promotional items and 1 regular code where:For M1,2 the forecast is...

View Article


Continue Using Expired Products/ Considering Shelf Life in Optimizer Run

Is there any Business scenario for this Expired Products/ why would any Business continue using Expired Products/ is there any scenario for this?  Thank you

View Article

dispose expired products/ Log not showing procurement cost only storage cost

When I run the Optimizer considering the Shelf Life and selecting the Dispose Expired Products in Optimizer Profile/ I'm not seeing the Procurement Cost only the Storage Cost ?  Thank you

View Article

Running Optimization and the Storage Cost is changing for Stock On Hand

Today is 05/20/2016 I have a Demand on 06/05 Stock on 05/20/2016 is 50000, Forecast on 06/04 is 50000/ and we have another Forecast on 06/08 of 10 / Now when I run the Optimizer without Shelf Life/ My...

View Article