Planned Order End date is different in ECC and APO.

$
0
0

Hi All,

 

Planned order created by SNP run (CTM) always has start and end date same in ECC.

 

The same planned order when we check in ECC its different but same in ECC.

There is one month of difference in ECC and APO End dates in palnned Orders.

 

Example:

 

Planned Order           Start Date                    End Date

     In APO                    19/06/2016             20/07/2013

     In ECC                    19/06/2016             19/06/2016

 

In PDS, activity duration (fixed) is 13 day for setup and handle.

 

 

 

How the activity duration (fixed) figure populates in PDS i believe it from work center ?

 

Please provide the info what could be the reason for SNP planned order have not the same  end date as APO.

 

Let me know if required any information to undersatnd the facts.

 

Regards,

Deepika