BW Reports for Materials Consumption
Hi, I'm looking for BW reports or any SAP Transactions that could provide monthly actual materials consumption/ usage for my plants. Please enlighten me if you know, thanks in advance. Regards,Christine
View ArticleRe: How to Change Planned Order Start Date & Time
Thanks Alok and AK, But still I'm not getting any BAPI to change Planned order start date and time in APO. /SAPAPO/RPT helps to change Order start date to future date; if the Order end date is in past....
View ArticleRe: BW Reports for Materials Consumption
Dear ChristineWhat do mean by consumption of material.Are you looking for sales orders for respective plant for each article. You can go to T-code VA05 in SAP ECC to see all the sales orders for...
View ArticleRe: SNP TLB - Load Method - Product wise loading - Product Mix Heavy/Light
Hi Debashis, Thanks for your information. i have gone through the given link and it doesn't explain about Product wise loading - Product Mix Heavy/Light loading method. can you help me on understand...
View ArticleAdding a field in the Selection of 9A_MALO extractor
Hi , 9A_MALO extractor is used to transfer the data from APO to BW in our client environment.Our requirement is to add one filter in APO based on the APO PLANNER(from a custom table) so that it will...
View ArticleRe: BW Reports for Materials Consumption
Dear Amol, In this context, i need to check how much materials have been used for each plant. Eg: raw material A usage in plant B, plant C and so on. The reason why i'm looking for this due to huge...
View ArticleRe: Backward Consumption Period different in ECC vs APO
Hi Marius, Could you let us know which method in the BADI can help in achieving user-defined (custom value calculated at code level) consumption period value to finally be sent to APO ? Thanks &...
View ArticleRe: Adding a field in the Selection of 9A_MALO extractor
Hi Pavan, In the Data Selection of Info package, you can use an ABAP routine for product. You can have this routine point to your custom table where you can maintain attributes like SNP Planner and...
View ArticleRe: Adding a field in the Selection of 9A_MALO extractor
Hi Abhishek, Thanks for your quick reply.Can you please elaborate your reply as I am new to this Extractor area so not able understand where to add the routine in APO.Can you please also let me know...
View ArticleRe: Capacity Consumption of Process Orders Query
Hi,If I can remember we did not find an APO based solution and had to revert some changes made in ECC and they stopped using scheduling type 3.Sorry I could not help further.
View ArticleRe: Use Period Factor - Field name REQ_COVER_TYPE - remove the tick
Hello, I found why is transfer: ECC in table T439A on field TERBV for MB the value 1. I maintained 3 and now I haven't any flag on use period factor for new products. Note 1931231:Scheduling indicator...
View ArticleNo requirements or dependent demand at Semi-Finished Goods from PPDS planned...
Hi Experts, Would like to ask you regarding requirements or dependent demand at Semi-Finished Goods (SFG). First, let me inform you that we are using PPM (both PPDS and SNP) in APO. For PPDS, it is...
View ArticleRe: Adding a field in the Selection of 9A_MALO extractor
Pavan, In order to run the extractor, you would already have an info package, transformation, DTP etc. The info package allows you to choose data selection i.e. which location-products you'd like to...
View ArticleRe: No requirements or dependent demand at Semi-Finished Goods from PPDS...
Found out the solution. It's all about in the CIF. Thanks anyway for the help. This can be closed. Regards,AA
View ArticleSAP APO PPDS Optimizer
Hi experts, If in APO PPDS for a material in a plant I have several resources and therefore I have several PDS, and the production orders saturate the capacity of a resource (PDS) When I execute the...
View ArticleAdding CVC's
Hi Gurus, I have a sales order for which GATP is getting triggered. Since the corresponding CVC's were not created earlier, i created the corresponding CVC. Later i updated the product allocation in...
View Articlemaximum how many characterstics we can do realignment
maximum how many characterstics we can do realignment
View ArticleRe: maximum how many characterstics we can do realignment
Hi SriniThere is no technical restriction on number of CVCs to be added into realignment table.But it´s good to realignment in small chucks because of run times. All the CVCs get locked during this...
View ArticleRe: Adding CVC's
Sandeep,Depends on your setup. Normally,1. create CVCs2. Maintain allocation qtys against cvcs in your planning book 3. copy cvcs to product allocation group4. copy allocation qtys to product...
View Article