Hi experts,
If in APO PPDS for a material in a plant I have several resources and therefore I have several PDS, and the production orders saturate the capacity of a resource (PDS)
When I execute the optimizer and it detects that a resource (PDS) is saturated the optimizer sends some production orders to another resource (PDS) to remove the overhead?
If the PPDS Optimizer does not send some production orders to other resource (PDS) what I have to do for it sends some production orders to other resource (PDS)?
Regards,