Hi Ashwani,
Assembly Scrap does not necessarily increase the Planned Order Qty to the produced. Try using lot sizes and you will be able to see the reduction in Planned Orders but the total sum of receipts will always be in conjunction (Lot Size, Rounding Value etc.) with the total demand. However, what Assembly Scrap does is increase the Dependent Demand of the components.
Regards