Hai ashwani,
Just check is you maintain assemble scrap % in MM mrp1 tab ? after that go to MM costing 1 tab, there under costing lot size option. Under the option we should maintain the enough quantity of lot size .
Ex : If you are maintain 2% assemble scrap , then you should maintain costing lot size option 50 pc . Then the assemble scrap is working properly.