Re: Incorrect Fixed duration in SNP PDS

$
0
0

Hello Sanjog, How did you resolved the issue?  We have a similar issue.   Duration is 80 hours fixed in ECC master receipe.    Resource is available for 8 hours per day, which means 10 days fixed duration.

 

In APO, fixed duration is 4 days (80 / 24 hours) = 3.33 so 4 days.

 

Ideally SNP fixed duration should be 10 days, as available SNP Bucket capacity is 8 hours per day and not 24 hours

 

Regards,

Bhavesh