Hi All,
Planned order created by SNP run (CTM) always has start and end date same in ECC and in APO both start and end date is different.
The same planned order when we check in ECC same order is having different end date from APO.
There is one month of difference in ECC in end date as compared to APO End dates in planned Orders.
Example:
Planned Order Start Date End Date
In APO 19/06/2016 20/07/2016
In ECC 19/06/2016 19/06/2016
In PDS, activity duration (fixed) is 13 day for setup and handle.
Please provide the info what could be the reason for SNP planned order have not the same end date as APO in ECC.
Let me know if required any information to understand the facts.
We have also ran the scenario with Heurstic planning run but no change and faced the same date issue in ECC and APO.
Regards,
Deepika