Alin,

Not using standard PP/DS.  PP/DS in general is planned infinitely; during planning there is no provision to accommodate selection of resources based upon capacity consumption.

 

It is possible for a planner to manually assign alternate resources using information found in the Planning Board..

 

If you need the capability of a planning engine that simultaneously considers both material shortages and also capacity shortages, both Optimizer and Capable To Match (CTM) are available.

 

Best Regards,

DB49