PDS Selection during PPDS planning run

$
0
0

Hello Experts,

 

When run heuristic (standard lots) for planning of receipts elements, the planned orders always select the PDS Version 001.

 

Is this standard that only PDS Version 1 gets selected during planning run ?

 

Is there a way where if resource of Version 1 is overloaded then PDS Version 2 get automatically selected during creation of planned orders ?

 

Regards

Alin