Dear All,
I'm planning a subcontracted product interactively with product heuristics from RRP3.
The planned delivery time in product master is 90 days & tranportattion time in lane is alos 90 days.
But for rquirement of 01/01/2016 (mm/dd/yyyy), system is generating PurRqs today itself.
Below are the screen shots.
When i change requirement date to 1st april 2016, then it is considering the 90 days lead time. See below start & end date.
I was expecting that the system will take account the lead time even when the requirement is today & subsequently the product will be available after 90 days from today.
I'm not sure any planning horizons (Stk trsfr, PP/DS Horizon, SNP Product Horizon) is having any impact.
Need help/guidance/suggestion in understanding this behaviour.
Thanks in aadvance.