Dear All,

 

I'm planning a subcontracted product interactively with product heuristics from RRP3.

The planned delivery time in product master is 90 days & tranportattion time in lane is alos 90 days.

But for rquirement of 01/01/2016 (mm/dd/yyyy), system is generating PurRqs today itself.

 

Below are the screen shots.

1.jpg

2.jpg

3.jpg

 

4.jpg

When i change requirement date to 1st april 2016, then it is considering the 90 days lead time. See below start & end date.

5.jpg

I was expecting that the system will take account the lead time even when the requirement is today & subsequently the product will be available after 90 days from today.

 

I'm not sure any planning horizons (Stk trsfr, PP/DS Horizon, SNP Product Horizon) is having any impact.

 

Need help/guidance/suggestion in understanding this behaviour.

 

Thanks in aadvance.