Hello Amol
You have mentioned the correct thing. But, my project requirement is such. Basically they release to SNP & then do a version copy. Then in simulation version version, they check the feasibility whether the demands could be fulfilled or not.
Now coming to the issue- two questions-
1. So ideally consumption should match or not? we are just CIFing the data from ECC to APO including all relevant category in APO
2. I observed only the PIRs in MD04 ( 350 quantities in continuous 8 months)& corresponding FC. Req in RRP3 in APO (400 quantities in the same 8 months). There is a mismatch - what I could think of is they did something in ECC (deleted the old one & created a new one) in such a way that the changes are not reflected in APO. But I don't have any proof for the same. Any reasons?
Regards
Som