Re: how to publish SNP planned order as planned order to ECC from APO in batch run.

$
0
0

S,

If the standard configuration for SNP Planned order is ECC Planned Order. Where can I see them in ECC?

MD04

Can you please share screen shot?

Not much to share.  It is exactly the same as a Planned order created via any other means.

In our case when we change the SNP planned to PPDS and publish them it converts them in Production order for Material A (finish good) and process order for Material B (Semi finish).

As I said earlier, I have never seen STANDARD CIF create a process order.

 

In your example, assuming standard CIF and assuming no special procurement keys in ECC, you would normally integrate a PPDS planned order for A to an ECC Planned order for A, which would generate a dependent requirement in ECC for B.  I don't know how you are getting the Process order.

 

With respect to SNP (which is the topic of this thread), in order to publish SNP orders to ECC, you would normally configure them so.  What are your SNP configuration settings?  In SCM, IMG > APO > Supply Chain Planning > Supply Network Planning > Basic Settings > Configure transfer to OLTP systems.

Capture.JPG

 

Best Regards,

DB49