Hello,
You can assign the Setup matrix to resource, system will check the setup matrix which is assigned to the resource in version 000. /SAPAPO/RES01 Change Resources: Header Data – Planning Version 000 screen, choose the Time-Cont. Capacity and assign Setup Matrix.
And in routing/recipe operation assign the setup group it will transfer to PPM/PDS via CIF and system will read the setup matrix from resource associated with the setup group operation.
Automatically determine the duration of the setup activities, during detailed scheduling
Please refer,
Setup Matrix - Detailed Scheduling Topics - SAP Library
Best Regards,
R.Brahmankar