Hi Jaisree,

 

Single-activity resources can only be used by one operation, whereas with multi-activity-resources, several operations can be scheduled at the same time. In your scenario, since you are having more than one operations and if you select the Several Operations Check box in workcenter it will be using Multi activity resource.

 

Regards,

Alok