Hi Experts,
I am trying to execute campaign planning in APO PPDS
Case 1:
I set the CAMPAIGN RELEVANCE indicator in APO Resource master
Created the Campaign profile in APO
Assigned the Setup matrix in the Resource master in APO
I executed the Campaign create Heuristic and also from the PPDS dashboard
But it is not helping me. I am getting the message in the dashboard "Campaign heuristic executed without any result"
Case 2:
I did all the above and mentioned the Setup group and key in the ECC Recipe and ciffed to APO PDS
On executing the heuristic from the dashboard, I am seeing the below message:
"Setup activity has atleast one mode that does not cover
Message No./SAPAPO/OM_ERROR253A
Sequence dependent setup activity has altleast mode that does not cover"""
Kindly guide me
Regards,
SCMLEARNER