Re: SNP planned orders are getting clubbed after heuristic at source

$
0
0

Hi Vinoth & Ada,

 

Thank you for your replies.

 

Here are the answers to your questions.....

 

1. How long is your SNP planning horizon - Executing planning interactively & TB profile IN PB is 156 weeks

 

2. SNP Prod Horizon - 26 weeks from Sunday at source

 

3. PP/DS Plng Time Fence - 70 days at source

 

4. Lot Sizing - Lot for lot at source & destination

 

5. Planning period - Weekly

 

6. Demands are in two different periods. One in week 42 of 2015 & other in week 5 of 2016

 

7. Lead time - 22 days

 

8. In which period does SNP heuristic put the planned order? - The second demand which is on      week5  of 2016

 

Below screen snaps FYR.

 

RRP3 view at destination - After heuristic at destination

1.jpg

 

RRP3 view at Source - After heuristic at destination

2.jpg

RRP3 view at Source - After heuristic at Source(only 1 planned order)3.jpg

Hope this clarifies.

 

Thank You!

 

 