Hi Vinoth & Ada,
Thank you for your replies.
Here are the answers to your questions.....
1. How long is your SNP planning horizon - Executing planning interactively & TB profile IN PB is 156 weeks
2. SNP Prod Horizon - 26 weeks from Sunday at source
3. PP/DS Plng Time Fence - 70 days at source
4. Lot Sizing - Lot for lot at source & destination
5. Planning period - Weekly
6. Demands are in two different periods. One in week 42 of 2015 & other in week 5 of 2016
7. Lead time - 22 days
8. In which period does SNP heuristic put the planned order? - The second demand which is on week5 of 2016
Below screen snaps FYR.
RRP3 view at destination - After heuristic at destination
RRP3 view at Source - After heuristic at destination
RRP3 view at Source - After heuristic at Source(only 1 planned order)
Hope this clarifies.
Thank You!