Goods Issue date on Holiday or Weekend

$
0
0

Hello Guru's,

 

 

When calculating my start date for a production Order, if my Goods Issue date falls on a holiday or on a weekend do the SNP heuristics push my start date backwards or does it move my demand date forward? Below is an example:

 

 

Demand Date: Aug 04 2015

 

Production Time : 2 days ( Calendar 5 days a week)

 

GI Time : 1 day ( Calendar 5 days a week)

 

GR Time : 1 Day  ( Calendar used 7 days a week)

 

 

In Above example:

 

I need product ready by Tuesday.

 

GR Day : Monday

 

GI Day : Sunday .  since this is a holiday do heuristic push by GI date to Friday or Monday?

 

 

Thank You in advance

 

 

Srikanth