I checked note 1168596 and found this "
a)If field 'Number of individual capacities' is equal 1 and the indicator of
field 'can be used by several operations' is not set, then the resource type is
Single Resource.
b)If field 'Number of individual capacities' is greather
than 1 or the indicator of field 'can be used by several operations' is set,
then the resource type is Multi Resource.
is there a way in this to convert it into Single Mixed.?
P.S: Currently my system settings are maintained as given in point "a)"