Re: SNP Planned Order Start date differs from ECC

$
0
0

Hi Arjen,  This is actually a Quality resource which has fixed duration.

In the example the duration in the operation is 288,000, which converts to 80 hours.  Although the SNP bucket capacity is 8 hours per day, in the PDS, instead of showing 10 days, it is showing up 4 days.

 

Calculation should work as below = 288,000 seconds / 3600 = 80 Hours.

80 Hours / 8 hours per day = 10 days. 

 

So SNP Fixed consumption should show up 10 days instead of 4 days.

 

Not sure why SNP PDS is not checking the available SNP Bucket Capacity, instead assuming 24 hours available??

 

Regards,