Hi,
Please check the below setting-
1) You have a valid PPM/PDS maintained in the system.
2) In SPRO under SNP basic settings-> Maintain SNP global settings-> GR for planned order fields
->select processing time
3) Valid handling resource is maintained at the location.
Thanks,
Rohit