Re: Multi-resource scheduling heuristic SAP_MULT_SCH problem

$
0
0

Hi Hrvoje,

     Thanks for the quick reply.

     I tried to modify the parameters on the heuristics to test around. It works, but as you mentioned that there are hidden restrictions, such as order duration (including GR time). Example: for the same resource, if there are orders with duration of 5 days and the ones are with 10 days. then it does not work as expected for both orders.

 

Thanks,

Ying