Hi Tiago,
Thanks for your reply.
We are running scheduling heuristic interactively in dashboard with the following setting :
Scheduling Mode : Find slot
Planning Direction: Forward
The Action in case of Scheduling error : "Sched. Infinitely and if Necessary Break Pegging Relationship."
We are trying to sequence the orders week by week. The issue is that system put the De-allocated orders at the beginning of the period in some case and in some cases the De-allocated orders are taking place at the end of period and we do not know why the system is behaving in this way.
Please let me know if you need any more details.
Best Regards
Deba