Hi Alin,
The fixed and variable durations and the corresponding capacity consumptions in the PDS are calculated based on the formulas informed in Scheduling tab of the Work Center (transaction CR02). Possibly if a scheduling formula for Processing results in a fixed duration for the mode in APO, it will have variable resource consumption. e.g. the duration is fixed, so to produce more units capacity consumption must be increased.
Regards,
Tiago