Hello experts,
I have the following scenario
Materials:
HALB: 157943
FERT: 157944
Resources
LIN_BAS
PRO_BAS
CarboC
The recipe for the FERT consumes the HALB in LIN_BAS and uses a secondary resource called CARBOC during the entire process. The Halb is produced in PRO_BAS.
The issue is that when we run the optimizer it delays the FERT order for a period of time equal to the time it uses the CARBOC. For example: the FERT order lasts 8 hours and the CARBOC is used during those 8 hours So if the HALB order finnishes at 18:00, the FERT order starts until 2:00 of the next day. This happens even when there is only one order for the FERT. I attached an image with the optimizer results.
What possible explanation could there be for this?