Dear All,
I searched in forum for the answer, but could not find, hence posting here.
I have created a calendar resource of category handling unit with productive time of 24 hours.
This resource has a factory calendar assigned with "only working days", i mean not working on saturday, sunday & holidays.
I have assigned this resource to a destination locatin in /sapapo/loc under resources tab >> handling resource >> "Resource inbound"
GRPT = 20 days defined in product master
So, for e.g. if requirement at destination is 29/07/2016, i was expecting to see start at source location 04/07/2016.
But the system is not considering working days from factory calendar, & i'm seeing the start date as 08/07/2016 which is just calendar days
Please help/suugest as how ti make system consider the factory calendar.