Can a SNP planned order be in past date ?. For an example an order created On week 1 and assume no plan happens till week 2 and on week 3rd first day I am seeing an SNP planned order in the past date(i.e. dated on 1st week) and now what is the influence of having an order in the past?. Do we want to delete these ordres before next optimizer runs or Optimizer will delete all these while planning and create a fresh in future dates.
↧