Quantcast
Channel: SCN: Message List - SAP Advanced Planning & Optimization (SAP APO)
Viewing all articles
Browse latest Browse all 2032

Re: MRP Contoller in APO Product Master

$
0
0

Alin:

 

As mentioned in previous posts, based off SAP's standard functionality the MRP controller in material master in ECC is not mapped to the production planner field in the APO. You would be needing an enhancement by using the following user exit.(APOCF005).

Use the following SAP OSS Note 520561-Maintaining product master in R/3 or in APO.

 

Regards


Viewing all articles
Browse latest Browse all 2032

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>