Re: How the days between Forcast entered and PReqs generated calculated.

$
0
0

Ayaskant,

 

If it some days, this means forward scheduling is happening. Example, requirement is for tomorrow and lead time is 10days then supply would be 10days from now.

 

On the same date means backward scheduling. If requirement is on 30th June and lead time is 10days. This means it would start on 20th June and will finish by required time.

 

Regards

Rahul