Hi guys,
I am new to the APO . Could someone help me on this issue?
1.
I am testing safety stock method AS/BS .
AS works fine. But BS does not work. Safety stock is reflected in the planning book.
I use the same way as i i did for AS. Set safety stock method_BS in product master and then go to Safety stock planning, click execute. Planning area is 9ASNP05.
It just does not work.
2. Second question is :
if I set the target days' supply to 5 days. And use safety stock method SZ to set safety days' supply to 5 days. Why most of the time target stock level is great than safety stock.
My understanding is I set them all to "5 days" which means target stock level should cover next 5 days'' demand and safety stock should also cover 5 days' demand. So they should be the same.
Could someone give me any advice?
Thanks a lot