Hi DB49
Thanks for your response. I had seen this link before posting the question as I am also thinking I am missing something. I have double checked the prerequisits....
1. Already provided settings for Check Mode & Instruction
2. Both material master has PPDS horizon maintained
3. PPDS Global & Default setting as Scheduling days (less than PPDS horizon)
4 'AY' added to the CHecking Control for Component
Not sure what is missing. I know it seems v standard situation. But again not yet seen the correct result. I will keep on looking at it. But meanwhile can you see the screen shots given earlier and see if anything is missing or have any suggestion.
Regards,
Jayanta