Hi Guys,
We are in process industry. I have a requirement where a phase has two different resource to be utilized in parallel. Considering the batch size and the capacity of the resource, one of the resource on the phase has a capacity constrain and we want to use similary resource for the same phase in parallel, so that the preceding phase continue to get the full batch for process. We are using CTM and has a CTM PDS created. I tried to define a secondary resource in recipe and CIF to APO. I notice it creates additional activity, rather it should have created additional capacity within the same operation where we added secondary resource to primary resource. Also while I perform CTM master Data check, it gives error for source inhouse "Activity has no output component and no successor". If you can suggest any user exit by which we can add the secondary resource as a capacity to the primary resource or suggest any alternate solution will be a great help.
Regards,
AB