In APO (Production) users observing strange behavior of Production orders. There is a between APO & ECC dates for production orders.
Actually user schedule production orders on Monday every week, these are appearing correctly on ECC side but in APO these orders are backdating (Means order of 30th week which in on Monday coming in 29th week). Which is causing double quantity of order in one week causing confusion for users. This is happening for several materials. I performed Reconciliation for those materials but it wont help.
I attached examples with details,
In first example,
For Material 7171/U0VF:
In AP1 order number 50586764 (528 qty.) is coming in 30th week instead of 31st week. Which is causing the 1056 qty. in week 30, but this not observed on ECC side which is causing confusion for users. There are more materials having same issue.
In second example,
For Material 12400/U0VF:
In AP1 order number 50586769 (6615 qty.) is coming in 30th week instead of 31st week. Which is causing the 13230 qty. in week 30, but this not observed on ECC side.
Can you please let me know is there any note I can apply to correct this or any other solution for the same
Thank You,
Prasad.