Hello Experts,
We are facing one issue in PP/DS, where sometimes when a planned order is converted to Production order the Operations are no more visible (see below) screenshot:
Initially we thought it happens when there is a resource overload situation. But we found another product on the same resource was not having this problem, even when resource was overloaded.
Any ideas what might be behind this behavior?
Many Thanks,
Bhuvan Paliwal