End date and start date determination (for TLB + requirements)

$
0
0

Good day all of you,

 

For both production requirements and shipping we face an interesting goal.

 

If a production order for one SKU is running from monday till thursday, TLB is calculating the availability date as the date where the goods are finished.

Not earlier than thursday, a proposal will be created to ship. However, in reallife, there's already lots of production ready on tuesday (and wednesday/thursday). Is there any way to cope with this situation? Instead of splitting the order in 5 pieces?

 

Same issue for looking at the requirements for this order. Seems like all the lower comp. requirements are needed on the start date.