Hi,
1. With external capacity the work center in APO will use the capacity (intervals & shifts) from ECC
2. Capacity variant is specific for APO. Will not be deleted. In this case you are no working with external capacity.
3. In ECC you can't create capacity variant (is specific for APO system)
Thanks,
Regards, Marius