Hi Joe,
I know that if in the ERP I have one routing with four alternative sequences in APO I will have one PDS with four modes, and the optimezer will be able to change planned orders beetwen these four modes.
My question was If I have several PDS with one mode each PDS, and the production orders saturate the capacity of a resource (PDS)
When I execute the optimizer and it detects that a resource (PDS) is saturated the optimizer sends some production orders to another resource (PDS) to remove the overhead?
If the PPDS Optimizer does not send some production orders to other resource (PDS) what I have to do for it sends some production orders to other resource (PDS)?
Regards,
Arnulfo Cordero Pradel